PROJECT TITLE:- DESIGN AND SUPERVISION OF WARE HOUSE, CLINIC, STAFF QUARTERS AND FST BASE FOR SIERRA LEONE BREWERY
NARRATIVE DESCRIPTION OF PROJECT:-
The Sierra Leone Brewery Ltd. in collaboration with Heineken supply chain was desirous in increasing the output of its products to meet the present demand and hence had to provide additional facilities which include the installation of seven new tanks. The scope includes the Construction of a warehouse, staff clinic, additional staff quarters, Fermentation Storage Tank (FST) base together with pipe bridge, separation drainages etc
Service Provided by TEDA: Architectural, Structural, Mechanical & Electrical Engineering Designs and
Quantity Surveying Services – Complete.
Supervision – complete
Client:- Sierra Leone Brewery Limited
Construction Period:- 2015 to 2019